  1. Bài 1: Vietnam beefs up militarization in WPS
  2. By Franco Jose C. Baroña
  3. July 16, 2023
  4. VIETNAM has tapped a private company to build an artificial island in the West Philippine Sea as part of its militarization efforts in areas that it claims, according to documents of the government project leaked to The Manila Times.
  5. The company was identified as the Airport Design and Construction Consultancy One Member Limited Liability Co. (ADCC), known as a top firm in Vietnam in the field of construction consultancy for aviation and airport engineering projects.
  6. Land features in the West Philippine Sea that will supposedly be militarized by Vietnam include Hizon (Pearson) Reef, Pigeon (Tennent) Reef and Maskardo (Barque Canada) Reef.
  7. These are also claimed by the Philippines, as they are covered by its 200-mile exclusive economic zone (EEZ), according to the documents.
  8. Aside from Vietnam and the Philippines, Hizon Reef is also claimed by China and Taiwan.
  9. In addition to the main feature, there is one outpost constructed on the fringing reef, which Vietnam first took possession of in 1978.
  10. Pigeon Reef, on the other hand, has been occupied by Vietnam since 1988. It is also claimed by China and Taiwan.
  11. Meanwhile, Vietnam first took possession of the Maskardo Reef in 1987. In addition to the main feature, there are three outposts constructed on the fringing reef.
  12. A source who requested anonymity for not being authorized to talk to the media said Vietnam is planning to build "a covert fortification, command fortification, firepower fortification, weapons storage fortification, traffic trench system, trench and related tactical items" in the territories mentioned.
  13. The source further told The Manila Times that the Vietnamese government is ready to send people to these land features, where they will set up residences.
  14. "They think that building military and civilian constructions and sending people to live in the islands [will prove that] those islands belong to them," the source said.
  15.  
  16. The source also revealed that Vietnam will increase the presence of its fishermen in the "vicinity waters of the above reefs because it is not only good for developing maritime economy but also defending their sovereignty."
  17. Documents obtained by the source showed that the scale of the Vietnam government's artificial island is vast. In Hizon Reef, the project will cover 19.5 km², in Pigeon Reef 23.4 km² and in Maskardo Reef 181 km².
  18. The same documents also showed that a total of 34 projects that will militarize the land features have been laid down.
  19. It was also learned that Vietnam plans to construct a 180-meter port in Sand Cay to dock its Gepard 3.9 class frigate, as well as fortifications, Battle Bunker and barracks.
  20. The scale of the project at Sand Cay will be about 100 km² when construction is finished.
  21. Sandy Cay is a sandbar that lies directly west of Pag-asa (Thitu) Island, also in the West Philippine Sea. It is the ninth-largest, and the fourth-largest former Vietnamese-administered, of the Spratly Islands.
  22. The island has been occupied by Vietnam since 1974, but is also claimed by the Philippines, China and Taiwan.
  23. Likewise, Binago (Namyit) Reef will expand to 173 acres and have two more ports to dock frigates such as the 3.9 Class Gepard.
  24. The source told The Manila Times that the Vietnamese government believes that signing the Code of Conduct (CoC) in the South China Sea "will maximize land reclamation, especially build military and civilian airports in islands with suitable conditions."
  25. Negotiations among Southeast Asian countries and China on the COC are expected to resume in Manila in August.
  26.  
  27. ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
  28. Bài 2: Vietnam builds more facilities in Spratlys
  29. By Franco Jose C. Baroña
  30. July 27, 2023
  31. VIETNAM is aggressively building permanent structures in the contested West Philippine Sea (WPS) based on a document obtained by The Manila Times titled "Planning of Construction Projects on Pearson Reef and Pigeon Reef in Spratly Islands," signed by Rear Admiral Tran Thanh Nghiem, commander of the Vietnam People's Navy, and dated March 27, 2023.
  32. Hizon (Pearson) Reef and Pigeon (Tennent) Reef are among the atolls in the Spratly Islands.
  33. The Philippines, China, Taiwan and Vietnam are also claimants to the reefs. Vietnam claimed possession of Hizon Reef in 1978 and Pigeon Reef in 1988.
  34. The document obtained by The Times said the Vietnamese are now building military installations and civilian residential housing in the area.
  35. In the paper, Vietnam noted that the "complicated and volatile international and regional situations in recent years," particularly the competing claims of sovereignty by several countries over areas in the South China Sea, have affected its economy and national defense "in multiple ways."
  36.  
  37. It added that the potential risks for maritime conflicts in the South China Sea and Spratly Islands increase regional uncertainties.
  38. The Vietnam People's Navy said the purpose and significance of implementing the Spratly Island Construction Planning is to "improve the management and defense capability of islands, boost the confidence and morale of officials and people in the islands, safeguard islands, continental shelf and the southern petroleum zone." It noted the strategic location of the atolls for military purposes.
  39. "Through expanding Pearson Reef and Pigeon Reef, building a battle group, we could develop a posture for attack and defense with the ability of mutual support. This is of long-term strategic significance since the control of waterways can be strengthened and military pressure to neighbor countries can be increased," it said in the document.
  40. The paper said the basis of the construction projects were the concluding comments of the working groups meeting presided over by Chief of General Staff Nguyen Tan Cuong held at the 2nd Conference Room of the Joint General Staff Operation Bureau between the Ministry of National Defense and Vietnam People's Navy on Spratly Islands construction planning held on April 18, 2021.
  41. The Vietnam People's Navy inspection group and Ministry of National Defense functional departments conducted a survey in the area from June 3 to 4, 2021.
  42. Decision 1492/QĐ-TTg issued by Vietnamese Prime Minister Phạm Minh Chín on the Master Planning Proposal on Promoting Capabilities to Govern and Defense Vietnam's Exclusive Economic Zone, Continental Shelf and Spratly Islands from 2020-2025 until 2030, the approved Vietnam People's Navy's Island Combat Plan, Navy Anti-Strike Plan, as well as the operation plan called "Dawn Support" also laid the groundwork for the island construction projects.
  43.  
  44. Projects that will be undertaken by Vietnam on Hizon Reef include civil works such as cultural houses, pagoda, reservoir, oil storage tank, desalination unit, wind and solar power systems.
  45. Currently, there are existing military engineering systems on the reef. These include a seaplane apron, Radar Station 44, 685th Brigade middle-range missile fortification, 37 mm anti-aircraft gun fortification, two grenade launcher fortifications, armored tank fortification, SU23 anti-aircraft fortification, recoilless gun fortification, 85 mm artillery fortification, and various trenches and covert fortifications.
  46. However, those military engineering systems cannot meet tactical demands, for they are in a state of disrepair and not functioning well because of the harsh environment.
  47. To satisfy the living and combat readiness training requirements of the troops stationed on the reef, Vietnam plans to continue expanding the island, as well as consolidate and improve military engineering and logistics support services.
  48. Projects lined up include the construction of a serial battle fortification aligned with the island's defensive combat plan.
  49. Based on the document, Hizon Reef will be continuously expanded to 760,000 square meters, with an expanded area of 19.5 hectares.
  50. In order to complete the construction of the most modern and largest dock of the future in the Spratly Islands, the area of the current dockyard will be increased to 38 hectares by dredging 16.3 hectares to the southwest from the existing base.
  51. The material excavated in the dredging process will be used for the reef's expansion.
  52. A breakwater with a length of 1,705 meters and a crown height reaching +4.5 meters will be built to protect the areas that are hydraulically reclaimed or newly built.
  53. Two logistics services will also be constructed in the north-western and south-western parts of the dock for the docking of Gepard 3.9 missile frigates and other military vessels with huge drafts.
  54.  
  55. Vietnam plans to maintain and upgrade its military installations on Hizon Reef, including its Middle-Range Missile Fortification, 85-mm Artillery Fortification, 85-mm Artillery Covert Fortification and 37-mm Antiaircraft Gun.
  56. Vietnam pointed out that the current projects basically meet the requirement of the living and combat readiness training for garrison troops, but with the increase in troops strength on the island, it is necessary to reconstruct and establish some infrastructures such as the military barracks.
  57. The Vietnamese government also plans to build civilian residential housing on Hizon Reef for about 50 households and the necessary infrastructure, including roads, clean energy systems, water supply systems, as well as wastewater and garbage treatment systems.
  58. It will likewise develop on the island a Production Park with "perfect" agriculture and stock farming facilities, aiming to provide food for nearby features, improve local production capacity and economy, as well as strengthen defense security.
  59. Trees will also be planted to improve the environment, serve as blindage and hide the fortifications.
  60. The same projects will also be undertaken on Pigeon Reef, which will be expanded to accommodate wider airport runways for future upgrades to a 2,800-meter-long and 800-meter-wide runway.
  61. Additional mooring buoys and navigational buoys will also be installed on the island.
  62. In addition, a sloping jetty will be constructed for berthing landing craft and seaplanes.
  63. The construction projects on Hizon and Pigeon Reefs will be managed directly by the Navy Command and designed by the Designing Institute of the Ministry of National Defense.
  64. The overall budget for the massive undertaking is 6,425 billion dong (roughly P14.829 million), including 3,745 billion dong (around P8.664 million) for Hizon Reef and 2,680 billion dong (around P6.188 million) for Pigeon Reef.